Telecommunications Client
Hong Kong

Hong Kong Data Center

Structure Tone was commissioned to construct a data center in Hong Kong for a leading telecommunications provider. This was the first data center built in Asia for the company. Work included:

  • the provision of 1000kVA of back up power service
  • FW200 fire protection, 617.5kVA UPS capacity plus 100% redundancy
  • 24 hour air conditioning
  • raised flooring, partitioning and finishing trades
  • coordination of all the cabling and cabinet installations

Mission Critical Construction

Over a three year period, Structure Tone managed the construction of the telecommunications company’s data centers. Work was completed around the world, including the following locations:

  • Beijing
  • Boston
  • Dallas
  • Dublin
  • Frankfurt
  • Hong Kong
  • London
  • New York
  • Paris


For More Information
Mike Kavanagh
+852 2838 8877
Email Mike